Confidential Client Chiller Replacement

MKK provided MEP design services for a large-scale chiller replacement at a confidentially-located office and data center. The chillers are used to cool the data center (raised floor area of approximately 40,600 SF) and office spaces. This facility operates 24 hours a day, seven days a week. Housed at the facility are 24-7 manned network operation control centers (NOCs), a data center, offices, and media center. The project was completed in multiple phases, with no shut-down and no loss of cooling. This was achieved through close coordination among the team members.

Area

95,000 SF

Related Projects

Project Details

X